Professional Scrum Master I (PSM I) — Question 37
Why does a Development Team need a Sprint Goal?
Answer options
- A. A Sprint Goal only gives purpose to Sprint 0.
- B. Sprint Goals are not valuable. Everything is known from the Product Backlog.
- C. The Development Team is more focused with a common yet specific goal.
- D. A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.
Correct answer: C
Explanation
The correct answer is C because having a common goal helps the Development Team stay aligned and focused on their objectives during the Sprint. Options A and B incorrectly downplay the significance of Sprint Goals, while D implies that the Sprint Goal is solely about implementing all selected Product Backlog items, which is not its primary purpose.