What two factors are best considered when establishing the Sprint length? (Choose two.)
Answer options
- A. The organization has mandated similar length sprints.
- B. The level of uncertainty over the technology to be used.
- C. The frequency at which team formation can be changed.
- D. The risk of being disconnected from the stakeholders.
Correct answer: B, D
Explanation
The correct answers, B and D, highlight the importance of managing technological uncertainty and maintaining stakeholder engagement in Sprint planning. Options A and C, while relevant to organizational practices, do not directly influence the decision on Sprint length.