Professional Scrum Master I (PSM I) — Question 160
What enhances the transparency of an Increment?
Answer options
- A. Doing all work needed to meet the definition of ג€Doneג€
- B. Reporting Sprint progress to the stakeholders daily
- C. Keeping track of and estimating all undone work to be completed in a separate Sprint.
- D. Updating Sprint tasks properly in the electronic tracking tool.
Correct answer: A
Explanation
Option A is correct because meeting the definition of 'Done' ensures that the Increment is fully complete, which enhances its transparency. The other options, while important for communication and tracking, do not directly contribute to the clarity of what constitutes a completed Increment.