Professional Scrum Master I (PSM I) — Question 157
A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?
Answer options
- A. Add security to the definition of ג€Doneג€.
- B. Tell the Product Owner to stop further development of features until the issues are fixed.
- C. Create a Product Backlog item for security.
- D. Go check with the testers.
- E. Ask the person to share the issue with the team as soon as possible.
Correct answer: E
Explanation
The correct answer is E because it's important for team transparency and collaboration that concerns are shared openly. This fosters a culture of trust and allows the team to address the issue collectively. Options A, B, C, and D do not promote immediate communication within the team and may delay resolving the security concerns.