Professional Scrum Master I (PSM I) — Question 149

Who determines how many Product Backlog items the Developers select for a Sprint? (Сhoose the best answer.)

Answer options

Correct answer: C

Explanation

The Developers are responsible for determining how many Product Backlog items they can commit to during a Sprint, based on their capacity and the Sprint goal. While the Product Owner provides the prioritized items, the actual selection is done by the Developers. Other roles, such as the Scrum Master or stakeholders, do not have the authority to make this decision.