Professional Scrum Master I (PSM I) — Question 149
Who determines how many Product Backlog items the Developers select for a Sprint? (Сhoose the best answer.)
Answer options
- A. The Scrum Master.
- B. The Product Owner.
- C. The Developers.
- D. The Scrum Team.
- E. The stakeholders attending Sprint Planning.
Correct answer: C
Explanation
The Developers are responsible for determining how many Product Backlog items they can commit to during a Sprint, based on their capacity and the Sprint goal. While the Product Owner provides the prioritized items, the actual selection is done by the Developers. Other roles, such as the Scrum Master or stakeholders, do not have the authority to make this decision.