Professional Scrum Master I (PSM I) — Question 145
Which of these may a Scrum Team deliver at the end of a Sprint? (Choose the best answer.)
Answer options
- A. An Increment of software with minor known bugs in it.
- B. Failing unit tests, to identify acceptance tests for the next Sprint.
- C. A single document, if that is what management asked for.
- D. A valuable, useful increment that meets the Definition of Done.
Correct answer: D
Explanation
The correct answer is D because it emphasizes delivering a valuable increment that satisfies the Definition of Done, ensuring quality and functionality. Options A and C do not guarantee a useful increment, while B fails to provide a deliverable at the end of the Sprint, as failing unit tests do not contribute to the final output.