Professional Scrum Master I (PSM I) — Question 143

Who does the work to make sure Product Backlog items conform to the Definition of Done? (Choose the best answer.)

Answer options

Correct answer: C

Explanation

The Developers are responsible for ensuring that Product Backlog items meet the Definition of Done, as they are the ones who actively work on delivering the product increment. While the Scrum Master, Product Owner, and Scrum Team have important roles, it is ultimately the Developers who implement the work and verify its completion according to the agreed-upon criteria.