Developers are self-managing, which of the following do they manage?
Answer options
- A. Sprint length.
- B. Sprint Backlog.
- C. Stakeholders for the Sprint Review.
- D. When to release, based on its progress.
- E. Product Backlog ordering.
Correct answer: B
Explanation
The correct answer is B, as developers have control over the Sprint Backlog, determining which tasks they will work on during the sprint. The other options, while related to the sprint process, are either managed by Scrum roles or influenced by external factors, making them less directly within the developers' control.