Professional Scrum Master I (PSM I) — Question 135
Choose two responsibilities of a self-organizing Development Team. (Choose two.)
Answer options
- A. Reorder the Product Backlog.
- B. Pull Product Backlog items for the Sprint.
- C. Do the work planned in the Sprint Backlog.
- D. Increase velocity.
- E. Report daily progress to stakeholders.
Correct answer: B, C
Explanation
The correct answers are B and C because a self-organizing Development Team is responsible for selecting items from the Product Backlog for the Sprint and executing the work defined in the Sprint Backlog. Options A, D, and E are not responsibilities of the Development Team, as reordering the Product Backlog is typically a Product Owner task, increasing velocity is a result rather than a responsibility, and reporting progress is generally done through Scrum ceremonies rather than being a direct responsibility.