Professional Scrum Master I (PSM I) — Question 135

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

Answer options

Correct answer: B, C

Explanation

The correct answers are B and C because a self-organizing Development Team is responsible for selecting items from the Product Backlog for the Sprint and executing the work defined in the Sprint Backlog. Options A, D, and E are not responsibilities of the Development Team, as reordering the Product Backlog is typically a Product Owner task, increasing velocity is a result rather than a responsibility, and reporting progress is generally done through Scrum ceremonies rather than being a direct responsibility.