Professional Scrum Master I (PSM I) — Question 114
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)
Answer options
- A. By ensuring the meetings start and end at the proper time.
- B. By keeping high value features high in the Product Backlog.
- C. By facilitating Scrum Team decisions.
- D. By removing impediments that hinder the Scrum Team.
Correct answer: C, D
Explanation
The correct answers are C and D because a Scrum Master facilitates decision-making within the Scrum Team and removes obstacles that impede progress. Options A and B, while important, do not directly address the core responsibilities of a Scrum Master in enhancing the team's productivity.