Professional Scrum Master I (PSM I) — Question 112
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Answer options
- A. Lead the discussions of the Development Team.
- B. Make sure that all 3 questions have been answered by each member of the team.
- C. Keep track of whether each team member has a chance to speak.
- D. Teach the Development Team to keep the Daily Scrum within the 15-minute time-box.
- E. All of the above.
Correct answer: D
Explanation
The correct answer is D because the Scrum Master is responsible for ensuring that the Daily Scrum remains within the 15-minute time-box to promote efficiency. While the Scrum Master may encourage participation (C) and ensure all questions are addressed (B), the primary role does not involve leading discussions (A) or making sure everyone speaks, as these can undermine the self-management of the team.