Professional Scrum Master I (PSM I) — Question 110
Which three of the following are feedback loops in Scrum? (Choose three.)
Answer options
- A. Sprint Review.
- B. Release Planning.
- C. Sprint Retrospective.
- D. Refinement Meeting.
- E. Daily Scrum.
Correct answer: A, C, E
Explanation
The correct answers are A, C, and E because the Sprint Review, Sprint Retrospective, and Daily Scrum are all designed to gather feedback and improve team processes. Release Planning and Refinement Meeting, while important, do not serve as direct feedback loops in the same way.