The Sprint Review is mainly an inspect and adapt opportunity for which group?
Answer options
- A. The Development Team and stakeholders.
- B. The Product Owner and Development Team.
- C. The Scrum Team and stakeholders.
- D. The Product Owner and management.
- E. The Development Team and management.
- F. The Product Owner and stakeholders.
Correct answer: C
Explanation
The correct answer is C, as the Sprint Review is designed for the Scrum Team, which includes the Development Team and stakeholders, to review progress and adapt the upcoming work. The other options either exclude essential participants like stakeholders or do not represent the Scrum framework accurately.