Professional Scrum Master I (PSM I) — Question 105
Who is responsible for tracking the remaining work of the Sprint?
Answer options
- A. The Development Team.
- B. The Scrum Master.
- C. The Project Manager.
- D. The Development Team is consultation with the Product Owner.
- E. The Product Owner.
Correct answer: A
Explanation
The Development Team is responsible for tracking their own work during the Sprint, as they are the ones performing the tasks. The Scrum Master facilitates the process, the Project Manager typically does not play a role in Scrum, and while the Product Owner collaborates with the team, they do not track the remaining work.