Professional Scrum Master I (PSM I) — Question 103
How is management external to the Scrum Team involved in the Daily Scrum?
Answer options
- A. The Scrum Master speaks on their behalf.
- B. Managers are not required at the Daily Scrum.
- C. Management gives an update at the start of each Daily Scrum.
- D. The Product Owner represents their opinions.
Correct answer: B
Explanation
The correct answer is B, as the Daily Scrum is primarily a meeting for the Scrum Team and does not necessitate the presence of managers. Options A, C, and D imply an involvement of management which is not aligned with the purpose of the Daily Scrum, where only the Scrum Team members discuss their progress and challenges.