Professional Scrum Master I (PSM I) — Question 100
For the purpose of transparency, when does Scrum say a valuable and useful increment must be available? (Choose the best answer.)
Answer options
- A. After the Acceptance Testing phase.
- B. Before the release Sprint.
- C. Every 3 Sprints.
- D. At the end of every Sprint.
- E. When the Product Owner asks to create one.
Correct answer: D
Explanation
The correct answer is D because Scrum mandates that increments must be delivered at the end of each Sprint to ensure transparency and continuous feedback. Options A, B, C, and E do not align with Scrum's framework, as they suggest infrequent delivery or conditions based on external requests rather than the structured cadence of Sprints.