For the purpose of transparency, when does Scrum say a valuable and useful increment must be available? (Choose the best answer.)

Answer options

Correct answer: D

Explanation

The correct answer is D because Scrum mandates that increments must be delivered at the end of each Sprint to ensure transparency and continuous feedback. Options A, B, C, and E do not align with Scrum's framework, as they suggest infrequent delivery or conditions based on external requests rather than the structured cadence of Sprints.