Professional Scrum Master I (PSM I) — Question 1
A Scrum Master is essentially the same thing as a traditional PM (Project Manager).
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is B because a Scrum Master focuses on facilitating the Scrum process and supporting the team, while a traditional Project Manager often has a more directive role in managing the project and its resources. The two roles have different responsibilities and approaches to project management.