Certified ScrumMaster (CSM) — Question 1

Which Scrum artifacts provide transparency and opportunities for inspection and adaptation?

Answer options

Correct answer: B

Explanation

The correct answer is B because the Sprint Backlog, Product Backlog, and Increment are key artifacts that promote transparency and facilitate the inspection and adaptation processes in Scrum. Options A, C, and D include artifacts that do not fully encompass the necessary elements for effective transparency and adaptability in Scrum practices.