SAFe Product Owner / Product Manager (POPM) — Question 2
Which of the following events shows how well the ART is progressing toward meeting the PI Objectives?
Answer options
- A. PO Sync
- B. Inspect and Adapt
- C. Backlog Refinement
- D. PI Planning
Correct answer: B
Explanation
The Inspect and Adapt event is specifically designed to assess progress toward the PI Objectives, allowing teams to evaluate their performance and make necessary adjustments. The other options, while important, do not focus on measuring progress in the same manner; for instance, PO Sync is more about aligning priorities rather than assessing outcomes.