SAFe Product Owner / Product Manager (POPM) — Question 11

Which is developed by teams and rolled up to the ART level during PI Planning?

Answer options

Correct answer: B

Explanation

The correct answer is PI Objectives, as these are specific goals that teams define during PI Planning to align with the overall objectives of the Agile Release Train (ART). Milestones, Dependencies, and ART PI Risks are important elements, but they do not represent the objectives set by the teams during this planning phase.