SAFe Agilist 6.0 – Leading SAFe — Question 9

What is an example of applying cadence and synchronization in SAFe?

Answer options

Correct answer: D

Explanation

The correct answer, D, is accurate because a PI Planning event is a key practice in SAFe that establishes cadence and synchronization among teams. The other options, while important in SAFe, do not specifically exemplify the concepts of cadence and synchronization like the PI Planning event does.