SAFe Agilist (SA) – Leading SAFe — Question 7
The program board shows which two items? (Choose two.)
Answer options
- A. Risks
- B. Capacity and load
- C. Significant dependencies
- D. Features
- E. Epics
Correct answer: C, D
Explanation
The program board is used to visualize important aspects of the project, including significant dependencies and features that are being worked on. While risks, capacity and load, and epics may be relevant to project management, they are not specifically shown on the program board.