SAFe Agilist (SA) – Leading SAFe — Question 20
What is an example of applying cadence and synchronization in SAFe?
Answer options
- A. Creating cross-functional teams
- B. Using a Portfolio Kanban system
- C. Allocating budgets to Agile Release Trains
- D. Conducting a PI Planning meeting
Correct answer: D
Explanation
Conducting a PI Planning meeting is a fundamental practice in SAFe that ensures teams synchronize their work and align their efforts over a defined cadence. The other options, while important in SAFe, do not specifically exemplify the concept of cadence and synchronization as effectively as PI Planning does.