SAFe Agilist (SA) – Leading SAFe — Question 12
During the PI Planning event, when are planning adjustments agreed upon?
Answer options
- A. During breakout sessions
- B. During the draft plan review
- C. During the management review and problem-solving
- D. During Scrum of scrums
Correct answer: C
Explanation
The correct answer is C because planning adjustments are typically finalized during the management review and problem-solving phase, where teams assess their plans and make necessary changes. The other options, while important parts of the PI Planning process, do not serve as the finalizing point for these adjustments.