SAP Certified Professional – SAP BTP Architect (2408) — Question 19
You have been hired as a solution architect and it’s your first day on the job. You participate in a meeting discussing the design and development of an extension to SAP S//4HANA Cloud. In the meeting, you are told:
“We have determined that the Business Partner (A2X) API in SAP S/4HANA Cloud is insufficient for our needs. Fortunately, the API is extendable via key user extensibility. We are currently creating a diagram with the technical building blocks of the extension”.
In which SAP Application Extension Methodology phase is the project?
Answer options
- A. Assess Extension Use Case
- B. Define Extension Target Solution
- C. Assess Extension Technology
Correct answer: B
Explanation
The project is in the 'Define Extension Target Solution' phase because the team is creating a diagram with the technical building blocks, indicating they are defining the solution they aim to implement. The 'Assess Extension Use Case' phase would involve evaluating potential use cases rather than defining a solution, and 'Assess Extension Technology' focuses on evaluating the technology aspects, which is not the current focus.