SAP Certified Specialist – SAP Activate for Cloud Solutions — Question 2
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Answer options
- A. During the Sprint Retrospective
- B. During the Sprint Review
- C. During the daily Scrum meeting
- D. During the user acceptance test
Correct answer: C
Explanation
The correct answer is C, as the daily Scrum meeting is a time for the team to align on progress and challenges, but formal confirmation of user story completion happens during the Sprint Review. Options A and B are incorrect as the Sprint Retrospective focuses on improving processes, not confirming story completion, and option D relates to testing rather than confirmation of completion by the product owner.