SAP Certified Specialist – SAP Activate for Cloud Solutions — Question 2

When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the daily Scrum meeting is a time for the team to align on progress and challenges, but formal confirmation of user story completion happens during the Sprint Review. Options A and B are incorrect as the Sprint Retrospective focuses on improving processes, not confirming story completion, and option D relates to testing rather than confirmation of completion by the product owner.