SAP Certified Application Associate – Procurement with SAP ERP 6.0 EHP7 — Question 1

Which of the following are required before you can purchase a product using the item category of vendor consignment in SAP Materials Management? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers are B and D because a confirmation control key is necessary to manage the procurement process for vendor consignment, and a material master is essential to define the product's attributes. Options A and C are not mandatory for this specific purchasing scenario.