SAP Certified Application Associate – SAP S/4HANA Sales (2022) — Question 18

For which type of outline agreement do you determine the material from the item category?

Answer options

Correct answer: B

Explanation

The correct answer is B, Scheduling agreement, as it necessitates the identification of materials linked to the item category for delivery scheduling. The other options, such as Condition contract, Value contract, and Quantity contract, do not require this specific determination of material based on item categories.