SAP Certified Application Associate – SAP S/4HANA Sales 1909 — Question 24

In which type of outline agreement would you see details of confirmed material quantities and delivery dates?

Answer options

Correct answer: C

Explanation

A Scheduling agreement is used to specify confirmed quantities of materials along with their delivery timelines, making it the correct choice. The other types of contracts, such as Quantity contracts and value contracts, do not typically include confirmed delivery dates.