SAP Certified Associate – SAP S/4HANA Sourcing and Procurement (2410) — Question 7

Which of the following prerequisites must be met for the system to check the shelf life of materials at goods receipt? (Choose two.)

Answer options

Correct answer: B, D

Explanation

Options B and D are correct because the shelf life expiration date check must be activated in Customizing for both the material type and the movement type to ensure proper validation at goods receipt. Options A and C are incorrect as they do not directly relate to the activation of checks necessary for the system to verify shelf life during this process.