SAP Certified Associate – SAP S/4HANA Sourcing and Procurement (2410) — Question 5
You want to use split valuation for your refurbishing process to differentiate between materials based on the condition of the material.
What do you need to consider for the accounting data of your material?
Answer options
- A. For the valuation area, the price control must be standard price.
- B. For each possible valuation type, the price control must be standard price.
- C. For the valuation area, the price control must be moving average price.
- D. For each possible valuation type, the price control must be moving average price.
Correct answer: B
Explanation
The correct answer is B because split valuation requires that each valuation type is controlled using a standard price to accurately reflect the different conditions of the materials. Options A and C are incorrect as they only address the valuation area rather than all valuation types, while option D incorrectly states that moving average price should be used for each valuation type.