SAP Certified Application Associate – SAP S/4HANA Sourcing and Procurement – Upskilling (2021) — Question 9
You send newly created purchase orders to a supplier via EDI, whereas quantity or price changes are transmitted by e-mail.
What prerequisites must be met if you are using the condition technique for message determination? (Choose three.)
Answer options
- A. The New Message Determination Process for Change Messages indicator is flagged in Customizing.
- B. The dispatch time related to the change message needs to be set to 1 (send with periodically scheduled job).
- C. You configure different message types for the New and Change print operations.
- D. The condition record contains the Price and Quantity fields.
- E. The Price and Quantity fields are relevant for printout changes.
Correct answer: A, B, E
Explanation
The correct answer includes A, which ensures that the system recognizes change messages, B, which sets the appropriate schedule for dispatching change messages, and E, which confirms that the relevant fields are included in printout changes. Option C is incorrect because it refers to the configuration of message types, which is not a prerequisite for the condition technique, and option D is not necessary for the message determination process to function properly.