SAP Certified Application Associate – SAP S/4HANA Sourcing and Procurement – Upskilling (2021) — Question 32

Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers are B and D because during an MRP Live run, Delivery schedule lines and Purchase requisitions can be created for externally procured materials. Purchase orders and Planned orders are not generated in this context.