SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 8
You cancel the technical completion of a work order.
What are the effects? (Choose two.)
Answer options
- A. Referenced notifications are put In Process again.
- B. Open purchase orders are recompiled.
- C. Open reservations are recompiled.
- D. Open purchase requisitions are recompiled.
Correct answer: C, D
Explanation
The correct answers are C and D because when the technical completion of a work order is canceled, it allows the open reservations and purchase requisitions to be recompiled for further processing. Options A and B are incorrect as they do not reflect the effects related to the cancellation of technical completion in this context.