SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 8

You cancel the technical completion of a work order.
What are the effects? (Choose two.)

Answer options

Correct answer: C, D

Explanation

The correct answers are C and D because when the technical completion of a work order is canceled, it allows the open reservations and purchase requisitions to be recompiled for further processing. Options A and B are incorrect as they do not reflect the effects related to the cancellation of technical completion in this context.