SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 4

Which operations are possible when you cancel the technical completion of a maintenance order? (Choose two.)

Answer options

Correct answer: B, D

Explanation

When a maintenance order's technical completion is canceled, it allows for the change of priority and the booking of a goods receipt. However, the status of 'Released' cannot be canceled, and estimated costs are typically fixed after completion, making options A and C incorrect.