SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 32
Which statements are correct for standard processes in PM/PS cost control? (Choose two.)
Answer options
- A. Maintenance costs can be settled to a network operation.
- B. Budget can be assigned to a WBS element.
- C. Maintenance order costs can be settled to a WBS element.
- D. Budget can be assigned to a maintenance plan.
Correct answer: B, C
Explanation
Options B and C are correct because budgets can indeed be assigned to WBS elements, and maintenance order costs can also be settled to these elements. Options A and D are incorrect as they do not accurately reflect the standard processes in PM/PS cost control.