SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 32

Which statements are correct for standard processes in PM/PS cost control? (Choose two.)

Answer options

Correct answer: B, C

Explanation

Options B and C are correct because budgets can indeed be assigned to WBS elements, and maintenance order costs can also be settled to these elements. Options A and D are incorrect as they do not accurately reflect the standard processes in PM/PS cost control.