SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 24
You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date.
The orders should be called 3 months before the planned date.
How can you set up the maintenance plan? (Choose two.)
Answer options
- A. Set the call horizon to 90 days.
- B. Set the call horizon to 25%.
- C. Set the call horizon to 75%.
- D. Set the offset to 3 months.
Correct answer: C
Explanation
The correct answer is C, as setting the call horizon to 75% allows for orders to be generated 3 months in advance of the 12-month cycle. Option A is incorrect because 90 days does not align with the required advance notice, while options B and D do not meet the specifications needed for this maintenance plan setup.