Which operations can the responsible person perform after a maintenance order is technically completed? (Choose three.)
Answer options
- A. Change the planned costs.
- B. Change the settlement rule.
- C. Update the estimated costs.
- D. Lock or unlock the order.
- E. Create an invoice receipt for delivered materials.
Correct answer: B, C, E
Explanation
The correct actions that can be performed after a maintenance order is technically completed include changing the settlement rule (B), updating the estimated costs (C), and creating an invoice receipt for delivered materials (E). Options A and D are incorrect because changing planned costs and locking/unlocking the order are not permitted after technical completion.