SAP Certified Application Associate – SAP SuccessFactors Employee Central Core — Question 15

A customer has scheduled an HRIS sync job, which includes mapping of job titles, to run every Friday. On Tuesday, an employee’s job title is changed via Manager Self-Service (MSS) to become effective on Thursday.
When will the synchronization happen?

Answer options

Correct answer: D

Explanation

The synchronization will occur on Friday when the scheduled sync job runs, which includes any job title changes made before that time. Changes made on Tuesday or effective on Thursday will only be included in the next scheduled sync, which is on Friday, making option D the correct choice. Options A, B, and C are incorrect as they do not align with the scheduled synchronization process.