SAP Certified Technology Associate – System Administration (SAP HANA as a Database) with SAP NetWeaver 7.5 — Question 21

What is the purpose of a pre-production system in an AS ABAP-based four-system landscape? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The pre-production system is designed to isolate changes and urgent corrections before they impact the production system, making options A and D correct. Option B is incorrect because while detecting errors is important, it is not the primary purpose of a pre-production system. Option C is also incorrect because urgent corrections are typically tested in the pre-production environment rather than implemented directly.