SAP Certified Application Associate – SAP S/4HANA Extended Warehouse Management — Question 6
Which documents are used in the expected goods receipt process during inbound processing in a decentralized SAP Extended Warehouse Management? (Choose two.)
Answer options
- A. Advanced shipping notification
- B. Inbound delivery
- C. Inbound delivery notification
- D. Expected goods receipt
Correct answer: A, D
Explanation
The correct answers are A and D because the Advanced shipping notification and the Expected goods receipt are key documents that facilitate the expected goods receipt process. Inbound delivery and Inbound delivery notification, while relevant, do not specifically pertain to the expected goods receipt aspect of the process.