SAP Certified Technology Associate – SAP HANA 2.0 (SPS05) — Question 36
What is the correct sequence of the following four steps when you restart the SAP HANA database system?
Answer options
- A. 1. Aborted transactions are rolled back. 2. Open transactions are recovered. 3. Row tables are loaded into memory. 4. Column tables are loaded.
- B. 1. Row tables are loaded into memory. 2. Open transactions are recovered. 3. Aborted transactions are rolled back. 4. Column tables are loaded.
- C. 1. Row tables are loaded into memory. 2. Column tables are loaded. 3. Open transactions are recovered. 4. Aborted transactions are rolled back.
- D. 1. Aborted transactions are rolled back. 2. Row tables are loaded into memory. 3. Open transactions are recovered. 4. Column tables are loaded.
Correct answer: B
Explanation
The correct order begins with loading row tables into memory, followed by recovering open transactions, rolling back any aborted transactions, and finally loading column tables. Options A, C, and D do not follow this sequence, resulting in an incorrect process for restarting the SAP HANA database system.