SAP Certified Associate – SAP Activate Project Manager (2022) — Question 4
Which task should you include in your procedure while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project? (Choose two.)
Answer options
- A. Review all the necessary Implementation Design Principles (IDPs).
- B. Review available SAP S/4HANA accelerators for the Data Management workstream.
- C. Review SAP S/4HANA best practices availability for your country.
- D. Review all the necessary leading practice process diagrams.
Correct answer: C, D
Explanation
The correct answers are C and D because reviewing the availability of SAP S/4HANA best practices for your region ensures alignment with local standards, while examining leading practice process diagrams helps in understanding the ideal processes to follow. Options A and B, while useful, do not directly pertain to the fit-to-standard analysis preparation.