SAP Certified Associate – SAP Activate Project Manager (2022) — Question 2
Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation? (Choose two.)
Answer options
- A. Create, review, and sign off the Project Charter.
- B. Discuss the Benefits and Functionality of SAP Analytics Cloud.
- C. Discuss the Benefits of SAP Data Warehouse Cloud.
- D. Create, review, and sign off the Create Project Management Plan.
Correct answer: A, C
Explanation
The correct answers, A and C, are focused on project initiation and understanding the benefits of SAP solutions, which are key activities during the Discover phase. Options B and D, while relevant to SAP solutions, do not pertain specifically to the Discover phase activities.