SAP Certified Associate – SAP Activate Project Manager (2022) — Question 16
Which of the following steps are part of the fit-to-standard process? (Choose two.)
Answer options
- A. Enable customers on standard business processes
- B. Document integration requirements
- C. Review Best Practices process flow
- D. Design to-be business process models
Correct answer: A, C
Explanation
The correct answers, A and C, focus on aligning customers with established business processes and assessing best practices, which are essential components of the fit-to-standard approach. Options B and D are not part of the fit-to-standard process as they pertain to integration and business process design, rather than standardization.