SAP Certified Associate – SAP Activate Project Manager (2013) — Question 2
What criterion does the Product Owner use to sequence the Product Backlog?
Answer options
- A. Resource availability
- B. Business priority
- C. Relative effort
- D. Complexity
Correct answer: B
Explanation
The Product Owner prioritizes the Product Backlog based on business priority to ensure that the most valuable items are completed first. Resource availability, relative effort, and complexity are important considerations, but they do not determine the sequence of the backlog as primarily as business priority does.