SAP Certified Associate – SAP Activate Project Manager — Question 1

What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? (Choose two.)

Answer options

Correct answer: A

Explanation

The correct answer, A, highlights that custom code is developed during the System Conversion process, while it is adjusted in the New Implementation phase. Other options incorrectly describe the processes related to data migration and transformation, as well as the handling of custom code, leading to confusion between the two transition paths.