Salesforce Certified Service Cloud Consultant — Question 97
Universal Containers is preparing to implement Service Cloud for its global Support team. Requirements gathering sessions have resulted in a large set of required deliverables.
What should a consultant recommend as the next step?
Answer options
- A. Prioritize the requirements based on who submitted them.
- B. Identify the requirements needed for initial GoLive.
- C. Provide a timeline that addresses all the requirements.
- D. Organize the requirements from the largest to smallest.
Correct answer: B
Explanation
The correct answer is B because identifying the requirements needed for the initial GoLive ensures that the most critical functionalities are addressed first, facilitating a successful launch. Options A, C, and D do not focus on the immediate needs for the initial deployment, which is essential for a successful implementation.