Salesforce Certified Sales Cloud Consultant — Question 88

Which two actions can a consultant take during the project planning phase to ensure client stakeholder goals are met? (Choose two.)

Answer options

Correct answer: B, D

Explanation

Establishing a stakeholder committee and meeting schedule (B) facilitates regular communication and collaboration, ensuring stakeholders' goals are prioritized. Acquiring the client stakeholder's key performance indicators (D) is essential for aligning the project objectives with their expectations. The other options, while useful, do not directly address stakeholder goals as effectively.