Salesforce Certified Development Lifecycle and Deployment Designer — Question 16
Universal Containers (UC) has multi-cloud architecture in a single org. The Sales Cloud dev team is working in a Dev Pro sandbox (DevPro1) of delivering a release in three months. The business requirements from Service Cloud warrant a quicker release in four weeks, but need part of the Sales Cloud work that is completed in DevPro1. The decision of using a separate Dev Pro sandbox (DevPro2) is still pending. The DevPro1 was upgraded to preview for next salesforce major release two weeks ago.
What should an Architect recommend?
Answer options
- A. DevPro1 cannot be cloned because it is on a different version from Production. Just create a new DevPro2, and migrate metadata from DevPro1.
- B. Ask the second work stream team to work on the same DevPro1 sandbox.
- C. Push back on the requirements because adding another work stream will bring some risks with it
- D. Clone the DevPro1 sandbox and name it DevPro2 for the second work stream to work on the Service Cloud requirements
Correct answer: C
Explanation
The correct answer is C because adding another work stream can lead to complications and risks, particularly with the timeline and version discrepancies. A and D are incorrect since cloning a sandbox on a different version is not feasible, and B is not advisable as it could cause conflicts and delays in both teams' work.